Pre-K through 12


Mid-del public schools                                   Program / construction MANAGEMENT 

CONSTRUCTION MANAGEMENT AT RISK                                                                    293,661 SQUARE FEET

CMSWillowbrook provided Pre-Bond Planning, Pre-Construction, and Construction Phase Services for new construction, renovations and additions of multiple elementary and middle schools.  Services included identification and implementation of program requirements, and design standards with multiple Architects and Engineers, preparation of estimates, site analysis, lifecycle and value analysis, and scheduling for the entire program.

All projects ran simultaneously: 
New EST Elementary 900 students, 
New Soldier Creek Elementary 900 students, 
Del City Elementary Renovation / Addition 750 students, 
Epperly Heights Elementary Renovation 750 students
 


BISHOP KELLEY HIGH SCHOOL
PHASE 2 STADIUM IMPROVEMENTS

GENERAL CONTRACT
17,046 SQUARE FEET

This project consisted of an addition and remodel of high school field house.  Which included a new football & baseball locker room, indoor batting facilities, weight room, coaches offices & a remodeled concession area.


BROKEN ARROW PUBLIC SCHOOLS
SOUTH INTERMEDIATE HIGH SCHOOL ADDITIONS / RENOATIONS

CONSTRUCTION MANAGEMENT AT RISK
39,000 SQUARE FEET

 

This public school project consisted of Pre-Construction and Construction Phase Services for renovating existing classrooms, reallocating spaces and an expansion for a new performing arts center. The new performing arts center includes a Drama / Black Box Theatre, Band Room, Choir Room, and Orchestra with Stage.


Chickasha Public Schools
Bill Wallace Early Childhood Education Center

CONSTRUCTION MANAGEMENT AGENCY
64,000 SQUARE FEET

This project included Pre-Construction and Construcion Phase Services for the new Bill Wallace Early Childhood Center. The design and construction of this project showcased a theme based on the Chisholm Trail. Many unique design elements and materials were incorporated to reflect the Chisholm Trail. Project is designed to be energy efficient and contains a geothermal system, and low flow plumbing fixtures. The overall design is based upon a "pod-concept" classroom layout, and the additions of a kitchen and dining area, media center, gymnasium, stage, and playground. A new enclosed corridor connects this new center to an existing elementary school.


Oakdale Public Schools
Multiple Projects

CONSTRUCTION MANAGEMENT AGENCY

CMSWillowbrook provided Pre-construction and Construction Phase services for a multiple additions and renovations. Scopes include new campus-wide utilities consisting of a high efficiency geo-thermal system, a new fire-loop, a new road and upgraded parking. The district has experienced a steady growth in enrollment. In order to accommodate the growth, we have worked with the district to upgrade playgrounds, and expand a number of classrooms, athletic facilities and parking. When the district was devastated by a tornado in the summer of 2003, we immediately responded to coordinate portable classrooms, permits and utilities until repairs could be completed.


Yukon Public Schools
New High School Complex

CONSTRUCTION MANAGEMENT         AT RISK

Yukon Public Schools New High School Project included Pre-construction and Construction Phase Services for the Complex including: 330,000 SF High School, 6,000 Seat Football Stadium, Wellness Center, 3,000 Seat Basketball Arena, Concessions, and New Turf & Track.